Extending an existing a planning permit

If your permit is due to expire and works have not been completed, you can apply for an extension of time to the commencement or completion date outlined in your existing planning permit either:

  • Before or within 6 months after the permit expiry date - where the use or development allowed by the permit has not yet started
  • Within 12 months after the permit expiry date - where the development allowed by the permit has lawfully started before the permit expires

 Fees for this type of application are as follows:

  • 1st Request    - $375
  • 2nd Request   - $475
  • 3rd Request + - $575

 Lodgement of an Extension of time 