Name Budget Locality Planning Design Procure Build Complete
Birdrock Beach Access Restoration Works Mount Martha
Bittern Public Toilet Renewal $300k Bittern
Blackspot - Wilsons Road - Road Safety $388,570 Mornington
Boneo - Browns Road - Motorcycle Safety Levy $323,885 Boneo
Boneo - Intersection of Browns Road and Jetty Road - Motorcycle Safety Levy $158,000 Boneo
Capel Sound: Broadway Road and Drainage Upgrade Stage 2 - 1.8million Capel Sound
Crib Point: Crib Point Landfill Capping Rehabilitation Works 1.5m Bittern
Crib Point:Creswell Street Development Contributions Plan - Water main Extension $300,000 Crib Point
Cricket Net Renewal Program – Multiple Sites
Dromana Bowls Subsidence Rectification $740,000 Dromana
Dromana: Dromana Recreation Reserve - Portable Change rooms 130k Dromana
Dromana: Dromana Recreation Reserve – New Netball Court $900,000 Dromana
Dromana: Hillview Reserve - Footpath and Playground $3.9 Million Dromana
Dromana: Marna Reserve Pavilion Upgrade $750,000 Dromana
Emil Madsen Sewer & Services Upgrade 1.4m Mount Eliza
Flinders Foreshore Pedestrian Safety $55,000 Flinders
Forest Drive – Black Length Project $240,700 Mount Martha
Hastings Senior Learning Hub 50,000 Hastings
Hastings: Foreshore Masterplan Implementation Hastings
Hastings: Hastings Boat Ramp Car park Upgrade 60,000 (Design Only) Hastings
Hastings: Hastings Foreshore Fitness Equipment $230,000 Hastings
Hastings: Revitalisation of Pelican Park Recreation Centre $5.7m Hastings
Hastings: Wallaroo Preschool Upgrade $746,730 Hastings
Main Ridge - Baldrys Road - Motorcycle Safety Levy $335,490 Main Ridge
Main Ridge - Main Creek Road - Motorcycle Safety Levy $601,350 Main Ridge
Main Ridge - Shands Road - Motor Cycle Levy $122,380 Main Ridge
Merricks North: Fenton Hall Remediation Works Merricks North
Mornington: Blackspot Program - Watt Road & Bruce Street Raised Safety Intersection $164,000 Mornington
Mornington: Civic Reserve Sports Pavilion Project $9,500,000 Mornington
Mornington: Community Animal Shelter Refurbishment $6 Million Mornington
Mornington: Dallas Brooks Reserve - Sport Fields, Carpark & Playground $9 Million overall Mornington
Mornington: Kathleen Crescent Drainage Improvements $300,000 Mornington
Mornington: Priority Footpath - Nepean Highway Mornington to Mt Eliza $100,000 (Design) Mornington
Mornington: Schnapper Point Boat Ramp and Jetty Upgrade TBC Mornington
Mount Eliza: Baden Powell Drive Footpath Stage 1 $130,000. (Design only) Mount Eliza
Mount Eliza: Blackspot Program - Mount Eliza Way $800,000 Mount Eliza
Mount Eliza: Canadian Bay Carpark $2.1 Million ($900,000 is subject to the current budget process) Mount Eliza
Mount Eliza: Emil Madsen Reserve - East Pavilion $10.5 m Mount Eliza
Mount Eliza: Emil Madsen Reserve - West Pavilion 500,000 (Design only) Mount Eliza
Mount Eliza: Emil Madsen Reserve Master Plan Stage 1 Mount Eliza
Mount Eliza: Landfill Capping Rehabilitation Works $2.5 Million Mount Eliza
Mount Martha Village Parking and Footpath, Watson Road $124,999 (Design) Mount Martha
Mount Martha: Blackspot Program – Raised Safety Platforms along Dunns Road $308,000 Mount Martha
Mount Martha: Briars - Boardwalk Mount Martha
Mount Martha: Briars - Homestead Project $450,000 Mount Martha
Mount Martha: Briars - Josephine's Restaurant Project Estimated $440,000 (Design only) Mount Martha
Mount Martha: Briars Class A Recycled Water Project $2.3 Million Mount Martha
Mount Martha: Briars Recycled Water Irrigation Infrastructure TBC Mount Martha
Mount Martha: Briars Sanctuary Expansion $2.3 Million Mount Martha
Mount Martha: Dunns Road Fitness Equipment Replacement $250,000 Mount Martha
Mount Martha: Landslide Reparation – Esplanade, Mt Martha Mount Martha
Mount Martha: Mount Martha North Foreshore Toilet Renewal $918,000 Mount Martha
Parking upgrades for Sorrento commercial activity centre and surrounds Sorrento
R2R - Eramosa Road East, Somerville - Road Rehabilitation 1.5m Somerville
Red Hill: Arthurs Seat Rd Black Spot / Pedestrian and Parking Project $497,952 Red Hill
Rosebud - Bayview Road - Motorcycle Safety Levy $383,000 Rosebud
Rosebud: Rosebud Memorial Hall $500,000 Rosebud
Rosebud: Tounnin Wominjeka Youth Hub $13 Million Rosebud
Rye & Tootgarook: Black spot program - Area Wide Safety Upgrade $1.67 Million Rye
Rye Skate Park Upgrade 1M (Stage 1) + $550K (Stage 2) Rye
Rye: Danny Street Drainage Upgrade $115,000 Rye
Rye: Foreshore Camping - Rye Township Plan Stage 1, Part C $1.5 Million Rye
Rye: Foreshore Park - Rye Township Plan Stage 1, Part D $2 Million Rye
Rye: Foreshore Promenade - Rye Township Plan Stage 1, Part B $2 Million Rye
Rye: Landfill Cell 2 Capping $19 Million Fingal
Rye: Melbourne Road and Peninsula Avenue - Raised Platforms $241,000 Rye
Safety Beach: Masterplan Implementation $3.4 Million Safety Beach
Safety Beach: Safety Beach Access Upgrades $400,000 Safety Beach
Shoreham Drainage: Marine Parade 40,000. Shoreham
Somerville - Tyabb Tooradin Road - Motorcycle Safety Levy $122,380 Somerville
Somerville to Baxter: Peninsula Trail - Shared User Path $7,700,000 BaxterSomerville
Somerville: Local Area Traffic Management - Black Spot Project $1,220,000 Somerville
Sorrento: Hotham Road Path Sorrento
Sorrento: Sorrento Museum Storeroom Addition $1.11 Million Sorrento
Sorrento: Sorrento Netball Courts $1.3m Sorrento
Tyabb: Tyabb Landfill Stormwater and Leachate Management $1.8 million Tyabb