Dromana: Dromana Bowls Subsidence Rectification

  • Project typeDrainage & Slope Stability
  • Project value$740,000
Aerial-view-of-Dromana-Bowls-Club.png

Project summary

There is a subsidence issue which is impacting the north-east corner of the bowling green at the Dromana Bowls Club. This has rendered the northern playing rink as unplayable due to the movement that has occurred on the green surface.

This project will:

  • Investigate the subsidence issue
  • Provide a design and recommendation to stop any future subsidence
  • Undertake subsidence stabilisation works
  • Repair the subsurface to the damaged green playing surface

 

Project timeline

Stage 1 – Complete (2025)

Geotechnical and feature level survey investigation and recommendation report of the subsidence issue.

Stage 2 – Current works (2026)

Concept and Detailed Design of the adopted proposed subsidence remediation works.

Planning and Victorian State Government authority approvals to undertake the proposed subsidence remediation works.

Stage 3 – Upcoming works (2027)

Major civil construction works for the subsidence rectification & subsurface repairs for the playing green.

The project works are due for completion by November 2027.

Location

1 Stawell Street, Dromana 3936  View Map

Google Map