Dromana: Gibson Street Path

  • Project typeFootpath Works
  • Project value$57,000
Dromana - Gibson Street Path.jpg

Footpath construction works are to be undertaken in Dromana to link Beach Street and Pier Street.

Works will be located in Beach Street extending from the existing path from Point Nepean Road to Gibson Street and in Gibson Street from Beach Street to match to the existing path between Pier Street and Noel Street.

Works will include a 1.5m wide exposed aggregate concrete path along with necessary pram crossings and service alterations.

Update: November 2017

A contract has been awarded however commencement has been postponed due to conflicting South East Water sewer upgrade works. Following a meeting with the contractor for South East Water they have advised that their works will not be completed until the end of November. As this is into the holiday period the footpath works will be delayed until February 2018.

Location

Gibson Street, Dromana 3936  View Map

Google Map