Red Hill: Mechanics Hall Improvements

  • Project typeBuildings
  • Project value$440,000
Completed Hall Toilet Extension.png

A new toilet facility has been constructed at the Red Hill Mechanics Hall. 

The design of the building is of a similar style to the current community hall. 

Disabled parking and a concrete pathway has also been included in the project which will make the building much more accessible for the whole community. 

A new water tank has been installed to help make the facility more environmentally friendly. 

Construction is began in late September 2021 and was completed by the end of February 2022. 

 

Update: June 2022

Location

19 Mechanics Road, Red Hill   View Map

Google Map