Boneo: Boneo Reserve Drainage Improvements
- Project typeDrainage and Slope Stability
- Project value$506,000
Drainage works are proposed within the Boneo Recreation Reserve to address public safety concerns associated with localised flooding.
It is proposed to pipe stormwater from the existing tennis court car park on the Eastern side of the reserve to discharge to the Western side of the reserve. Works will include the directional drilling to install a new stormwater pipe for approximately 200 metres along with the installation of a small wetland at the discharge location.
Detailed design and the preparation of a cultural heritage management plan is now complete.
The project is expected to be delivered by the end of 2023.
Update: May 2023.
Location
570 Boneo Road, Boneo 3936 View Map
-38.4112658,144.887222
570 Boneo Road ,
Boneo 3936
570 Boneo Road ,
Boneo 3936